Scheduled Inspection Requests

These are the scheduled inspections.

You can save a copy by selecting all (Ctrl A) and paste into Excel (Ctrl V).

You can also print this page File > Print (Ctrl P).

Date
Time
Company
Inspection Type
Inspection Notes
QC Contact
QC Phone
Facility No
Location
Detailed Location
Assignee
Cancelled
02/13/2025
0500
J. Simmons Group, Inc.
Concrete Sampling
Road 9 and pour back demo at 221/D222202 7" slump
Victoria
2812212915
025 Site Civil
Site Civil
Road 9 and pour back demo at 221
02/12/2025
1550
J. Simmons Group, Inc.
Closed Form/Pour Card Inspection
Road 9 and pour back demo at 221
Victoria
2812212915
025 Site Civil
Site Civil
Road 9 and pour back demo at 221
02/07/2025
1000
Balfour Beatty
Visual Inspection - Add Notes
Visual inspection for Basin 6
Poonam
8329779803
243 Flocculation and Sedimentation Train 3
North Plant
243 basin #6
02/06/2025
0830
Balfour Beatty
Visual Inspection - Add Notes
Paint PDR piping inside
mhoy
281-865-8418
253 Ozone Contractor 3
North Plant
Roof top
Oznel
02/05/2025
11.00
Pepper Lawson - YP
Closed Form/Pour Card Inspection
none
Troy Continenetal
979-777-1979
035 Site Yard Piping
Yard Piping
road-trench mow strip pond 8-9
02/05/2025
14.00
Pepper Lawson - YP
Concrete Sampling
none
Troy Continental
979-777-1979
035 Site Yard Piping
Yard Piping
road-mow strip trench pond 8-9
08/30/2024
1000
Balfour Beatty
Visual Inspection - Add Notes
Concrete Surface Finish
Zach R
832.975.2802
254 Ozone Contractor 4
North Plant
254 - South Exterior Wall
Dan N
08/09/2024
1300
Balfour Beatty
Electrical 4 - Ground Resistance/High Potential
resistance test.
Warren Davis
832-373-5796
215 Pretreatment Chemical Facility 5
North Plant
North West corner of 215
Robert J
07/20/2024
1000
Balfour Beatty
Water Tightness/Static Head/Leak
NO INSPECTION - Leak test day #3 (SOAK)
Saif
8323357393
802 Basin Drain Pump Station 2
North Plant
802
07/19/2024
1000
Balfour Beatty
Water Tightness/Static Head/Leak
NO INSPECTION - Leak test day #2 (SOAK)
Saif
8323357393
802 Basin Drain Pump Station 2
North Plant
802
07/19/2024
1100
Balfour Beatty
Visual Inspection - Add Notes
Concrete Surface Finish
Zach R
8329752802
244 Flocculation and Sedimentation Train 4
North Plant
244 - Basin 8 Floc Basin: North Interior
Larry C
07/18/2024
0900
Balfour Beatty
Visual Inspection - Add Notes
Concrete Surface Finish Sign Off
Zach R
832.975.2802
244 Flocculation and Sedimentation Train 4
North Plant
244 - Basin 8 Floc: North Interior Wall
Dan N