These are the scheduled inspections.
You can save a copy by selecting all (Ctrl A) and paste into Excel (Ctrl V).
You can also print this page File > Print (Ctrl P).
Date | Time | Company | Inspection Type | Inspection Notes | QC Contact | QC Phone | Facility No | Location | Detailed Location | Assignee | Cancelled |
|---|---|---|---|---|---|---|---|---|---|---|---|
02/26/2025 | 1100 | Balfour Beatty | Visual Inspection - Add Notes | Chain and flight 200 hours run test - Day #7 | Saif | 8323357393 | 612 Liquid Residuals Clarifier Facility 2 | North Plant | 612 | ||
02/25/2025 | 0800 | Balfour Beatty | Visual Inspection - Add Notes | Paint 24" ductile | mhoy | 281-865-8418 | 504 Gravity Sludge Thickener Complex 4 | North Plant | North side at USDS | ||
02/25/2025 | 0830 | Balfour Beatty | Visual Inspection - Add Notes | Paint ductile | mhoy | 281-865-8418 | 802 Basin Drain Pump Station 2 | North Plant | Inside | ||
02/25/2025 | 0900 | Balfour Beatty | Visual Inspection - Add Notes | Paint PVC piping | mhoy | 281-865-8418 | 202 Chloride Dioxide Facility 2 | North Plant | Inside building main room | ||
02/25/2025 | 0930 | Balfour Beatty | Visual Inspection - Add Notes | Paint PVC piping | mhoy | 281-865-8418 | 216 Pretreatment Chemical Facility 6 | North Plant | Inside main room | ||
02/25/2025 | 1000 | Balfour Beatty | Visual Inspection - Add Notes | Deficiency Tracker Item - J Hook Sealant Fix | Zach R | 8329752802 | 218 Pretreatment Chemical Facility 8 | North Plant | 218 - PC Tanks | ||
02/25/2025 | 1000 | Balfour Beatty | Visual Inspection - Add Notes | Final paint inspection on PPW piping before piping gets insulated. | mhoy | 281-865-8418 | 217 Pretreatment Chemical Facility 7 | North Plant | North road | ||
02/25/2025 | 1030 | Balfour Beatty | Visual Inspection - Add Notes | Paint PEN line | mhoy | 281-865-8418 | 243 Flocculation and Sedimentation Train 3 | North Plant | Rooftop | ||
02/25/2025 | 1100 | Balfour Beatty | Visual Inspection - Add Notes | Paint PEN line | mhoy | 281-865-4818 | 244 Flocculation and Sedimentation Train 4 | North Plant | Roof top | ||
02/25/2025 | 1100 | Balfour Beatty | Visual Inspection - Add Notes | Chain and flight 200 hours run test - Day #6 | Saif | 8323357393 | 612 Liquid Residuals Clarifier Facility 2 | North Plant | 612 | ||
02/25/2025 | 1100 | Balfour Beatty | Visual Inspection - Add Notes | Chain and flight 200 hours run test - Day #6 | Saif | 8323357393 | 243 Flocculation and Sedimentation Train 3 | North Plant | 243 Basin #6 | ||
02/25/2025 | 1130 | Balfour Beatty | Visual Inspection - Add Notes | Paint 8" CDS on roof top | mhoy | 281-865-8418 | 223 Rapid Mix Train 3 | North Plant | Roof top |