Scheduled Inspection Requests

These are the scheduled inspections.

You can save a copy by selecting all (Ctrl A) and paste into Excel (Ctrl V).

You can also print this page File > Print (Ctrl P).

Date
Time
Company
Inspection Type
Inspection Notes
QC Contact
QC Phone
Facility No
Location
Detailed Location
Assignee
Cancelled
03/28/2025
0800
Harper Bros
Field Density/Compaction/Subgrade
66" RWL Densities
Paul Hernandez
8325401585
025 Site Civil
Site Civil
North Tunnel
Damon O
03/26/2025
1300
Balfour Beatty
Visual Inspection - Add Notes
Surface prep on 78"
mhoy
281-865-8418
223 Rapid Mix Train 3
North Plant
North Vault
Damon O
03/19/2025
1300
Balfour Beatty
Visual Inspection - Add Notes
Basin Walk
Poonam
8329779803
503 Gravity Sludge Thickener Complex 3
North Plant
503 USDS
03/14/2025
10
Industrial TX
Visual (VT)/CWI Inspection
Finish coat on the concrete barrier bollards - All day
Edwin P
8324984994
075 Main Entrance Guard House
Site Civil
Guardhouse
03/14/2025
10
Industrial TX
Drilling/Doweling/Epoxy/Pull Test
Drilling min 6" for Bollards / Epoxy and SS 7/8" threaded bolts
Edwin P
8324984994
075 Main Entrance Guard House
Site Civil
Guardhouse
03/13/2025
1000
Balfour Beatty
Visual Inspection - Add Notes
Basin inspection
Poonam
832-335-7393
504 Gravity Sludge Thickener Complex 4
North Plant
504 USDS
03/13/2025
9
Industrial TX
Visual (VT)/CWI Inspection
Concrete barrier bollards - Continue putting the first coat on them - All day long
Edwin Pena
8324984994
075 Main Entrance Guard House
Site Civil
Guardhouse
Damon O
03/10/2025
1000
Balfour Beatty
Visual Inspection - Add Notes
612 Basin inspection
Poonam
8329779803
612 Liquid Residuals Clarifier Facility 2
North Plant
612 Clarifed Recycle Pump Station
Damon O
02/27/2025
1100
Balfour Beatty
Visual Inspection - Add Notes
Chain and flight 200 hours run test - Day #8 ( final)
Saif
8323357393
612 Liquid Residuals Clarifier Facility 2
North Plant
612
02/27/2025
1100
Balfour Beatty
Visual Inspection - Add Notes
Chain and flight 200 hours run test - Day #8 (Final)
Saif
8323357393
243 Flocculation and Sedimentation Train 3
North Plant
243 Basin #6
02/27/2025
1100
Balfour Beatty
Visual Inspection - Add Notes
Chain and flight 200 hours run test - Day #7
Saif
8323357393
612 Liquid Residuals Clarifier Facility 2
North Plant
612
02/26/2025
1100
Balfour Beatty
Visual Inspection - Add Notes
Chain and flight 200 hours run test - Day #7
Saif
8323357393
243 Flocculation and Sedimentation Train 3
North Plant
243 Basin #6