Scheduled Inspection Requests

These are the scheduled inspections.

You can save a copy by selecting all (Ctrl A) and paste into Excel (Ctrl V).

You can also print this page File > Print (Ctrl P).

Date
Time
Company
Inspection Type
Inspection Notes
QC Contact
QC Phone
Facility No
Location
Detailed Location
Assignee
Cancelled
04/30/2024
0900
J. Simmons Group, Inc.
Concrete Sampling
Pond 6 West
Victoria
2812212915
025 Site Civil
Site Civil
Pond 6 West
Sam K
04/29/2024
0700
Pepper Lawson - YP
Open Form Inspection
concrete collars around Boxes north of HSPS 401
Herman Martin
281.610.1033
035 Site Yard Piping
Yard Piping
North HSPS 401
Kermit Thomas
04/29/2024
0800
Pepper Lawson - YP
Drilling/Doweling/Epoxy/Pull Test
Pipe bollards ARV pads Phase 1.
Herman Martin
281.610
035 Site Yard Piping
Yard Piping
Phase 1 ARV pads
Kermit Thomas
04/29/2024
0800
Balfour Beatty
Visual Inspection - Add Notes
TX Moisture - On Going Work
Zach R
832.975.2802
202 Chloride Dioxide Facility 2
North Plant
202 - Exterior Water Repellant Application / Control Joint Sealant
Roderick F
04/29/2024
0830
Pepper Lawson - HSPS
Visual Inspection - Add Notes
Grouting of pipe supports at 402
Rene Hinojosa
7139722224
402 HSPS 2
South Plant
HSPS 402
Salim S
04/29/2024
0830
Balfour Beatty
Visual Inspection - Add Notes
Paint Piping
mhoy
281-865-8418
503 Gravity Sludge Thickener Complex 3
North Plant
Basement
Bill B
04/29/2024
0900
Pepper Lawson - HSPS
Visual Inspection - Add Notes
Coating of pipe at 402
Rene Hinojosa
7139722224
402 HSPS 2
South Plant
HSPS 402
Bill B
04/29/2024
0900
Balfour Beatty
Field Density/Compaction/Subgrade
JSG - On Going Work
Zach R
832.975.2802
254 Ozone Contractor 4
North Plant
254 - Exterior Perimeter Walls
Sam K
04/29/2024
0900
Balfour Beatty
Visual Inspection - Add Notes
CMU Bond Beam
Zach R
832.975.2802
262 Ozone Generation Facility 2
North Plant
262 - Interior 8” Walls Bond Beam (5th Bond Beam)
Roderick F
04/29/2024
0915
Pepper Lawson - YP
Field Density/Compaction/Subgrade
24" PW
Saul Castellanos
281.610.1033
035 Site Yard Piping
Yard Piping
C4-2C North of 402
Kermit Thomas
04/29/2024
0915
Balfour Beatty
Visual Inspection - Add Notes
Visual Inspection
Zach R
832.975.2802
802 Basin Drain Pump Station 2
North Plant
802 - 16” PDR Form Removal
Salim S
04/29/2024
0930
Pepper Lawson - YP
Field Density/Compaction/Subgrade
10" DEC Blowoff
Saul Castellanos
281.610.1033
035 Site Yard Piping
Yard Piping
C3-2A meets C2-2AB Crossroads
Kermit Thomas
04/29/2024
0945
Pepper Lawson - YP
Cathodic Protection
10" DEC Blowoff
Saul Castellanos
281.610.1033
035 Site Yard Piping
Yard Piping
Crossroads C2-2AB and C3-2A
John Deaton
04/29/2024
1000
Pepper Lawson - YP
Cathodic Protection
8" PW
Arron Powell
281.610.1033
035 Site Yard Piping
Yard Piping
C3-2B
John Deaton
04/29/2024
1000
Balfour Beatty
Concrete Sampling
Class D2 4500 - 5yds
Greg S
832.975.2802
223 Rapid Mix Train 3
North Plant
223 & 224 - 78” Pipe Saddles
Roderick F
04/29/2024
1000
Balfour Beatty
Closed Form/Pour Card Inspection
Reinforcing Steel, Concrete Forms
Zach R
832.975.2892
251 Ozone Contractor 1
North Plant
251 - South Exterior 10” PDR Supports
Roderick F
04/29/2024
1100
Balfour Beatty
Water Tightness/Static Head/Leak
Water Tightness Test. Final Readings.
mhoy
281-865-8418
253 Ozone Contractor 3
North Plant
Roof Top
Salim S
04/29/2024
1100
Balfour Beatty
Hydrostatic/Pneumatic Pressure Chlorine Residual Test
Leak Test
Mike H
832.975.2802
253 Ozone Contractor 3
North Plant
253 - Quantitative Leak Test (Final Reading)
Salim S
04/29/2024
1100
Pepper Lawson - YP
Field Density/Compaction/Subgrade
4" SSF
Arron Powell
281.610.1033
035 Site Yard Piping
Yard Piping
Phase 2 North road between 216/217
Kermit Thomas
04/29/2024
1550
J. Simmons Group, Inc.
Closed Form/Pour Card Inspection
Pond 6 West
Victoria
2812212915
025 Site Civil
Site Civil
Pond 6 West
Sam K
04/29/2024
815
Pepper Lawson - YP
Field Density/Compaction/Subgrade
4" SSF
Andrew McWilliams
281.610.1033
035 Site Yard Piping
Yard Piping
C3-2B
Kermit Thomas
04/26/2024
0700
Fisk Electric
Electrical 2 - Ductbank/Exterior
Conduit Cover - 274MVT00002 Secondary Riser
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 274
John Deaton
04/26/2024
0730
Fisk Electric
Field Density/Compaction/Subgrade
Backfill - 273MVT00001/ 00002 Secondary duct banks.
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 273
John Deaton
04/26/2024
0830
Pepper Lawson - YP
Cathodic Protection
24" PW "Air Gap"
Saul Castellanos
281.610.1033
035 Site Yard Piping
Yard Piping
North of HSPS 402/111 C4-2C
John Deaton
04/26/2024
0900
Fisk Electric
Concrete Sampling
Appro. 3yds - 2500 psi - Class A - 274MVT00002 Secondary Riser
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 274
John Deaton
04/26/2024
0915
Pepper Lawson - YP
Cathodic Protection
10" Blowoff
Felix rodRiguez
281.610.1033
035 Site Yard Piping
Yard Piping
Phase 2 East Road
John Deaton
04/26/2024
0930
Pepper Lawson - YP
Cathodic Protection
4" SSF
Andrew McWilliams
281.610.1033
035 Site Yard Piping
Yard Piping
East of 282
John Deaton
04/26/2024
1000
Balfour Beatty
Closed Form/Pour Card Inspection
Reinforcing Steel, Concrete Forms
Zach R
832.975.2802
223 Rapid Mix Train 3
North Plant
223 & 224 Pipe Saddles
Roderick F
04/26/2024
1000
Pepper Lawson - YP
Cathodic Protection
8" PW
Arron Powell
281.610.1033
035 Site Yard Piping
Yard Piping
North road Between 215/216
John Deaton
04/26/2024
1100
Balfour Beatty
Visual Inspection - Add Notes
TX Moisture - On Going Work
Zach R
832.975.2802
241 Flocculation and Sedimentation Train 1
North Plant
241 - Elevated Walkway Expansion Joint Sealant
Roderick F
04/26/2024
1130
Balfour Beatty
Visual Inspection - Add Notes
Visual Cleanliness
Zach R
832.975.2802
202 Chloride Dioxide Facility 2
North Plant
202 - Interior CMU Wall Cleanliness
Roderick F
04/26/2024
1300
Fisk Electric
Field Density/Compaction/Subgrade
Backfill - 274MVT00002 Secondary riser
Scott Peterson
291-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 274
John Deaton
04/26/2024
1300
Balfour Beatty
Visual Inspection - Add Notes
Bond Beam
Zach R
832.975.2802
262 Ozone Generation Facility 2
North Plant
262 - Interior 8” CMU Wall Bond Beam (6th Bond Beam)
Roderick F
04/25/2024
0700
Fisk Electric
Electrical 2 - Ductbank/Exterior
Conduit Cover Insp. - 273MVT00001/ 00002 Secondary Duct Bank
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 273
John Deaton
04/25/2024
0900
Fisk Electric
Concrete Sampling
20+ - 2500 psi - Class A
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 273
John Deaton
04/25/2024
0900
Pepper Lawson - YP
Cathodic Protection
Cathodic on Fire hydrant install
Felix rodriguez
281.610.1033
035 Site Yard Piping
Yard Piping
C3-2A North
John Deaton
04/25/2024
0915
Pepper Lawson - YP
Cathodic Protection
24" PW North 4022
Saul Castellanos
281.610.1033
035 Site Yard Piping
Yard Piping
C4-2C
John Deaton
Y
04/25/2024
1000
Balfour Beatty
CLSM/Flowfill Sampling
10+ yards of CLSM
Warren Davis
832-373-5796
274 Pretreatment Service Building 4
North Plant
South side of building
John Deaton
04/25/2024
1100
Balfour Beatty
Visual Inspection - Add Notes
Visual Inspection
Zach R
832.975.2802
241 Flocculation and Sedimentation Train 1
North Plant
241 - Elevated Walkway Expansion Joint Sealant
Roderick F
Cancelled
04/25/2024
1300
Balfour Beatty
Visual Inspection - Add Notes
CMU Cleanliness
Zach R
832.975.2802
202 Chloride Dioxide Facility 2
North Plant
202 - Interior West CMU Wall
Roderick F
04/25/2024
1400
Balfour Beatty
Closed Form/Pour Card Inspection
Reinforcing Steel, Concrete Forms
Zach R
832.975.2802
224 Rapid Mix Train 4
North Plant
223 & 224 - 78” Pipe Saddles
Roderick F
Cancelled
04/25/2024
1500
Balfour Beatty
Visual Inspection - Add Notes
CMU Bond Beam
Zach R
832.975.2802
262 Ozone Generation Facility 2
North Plant
262 - Interior 8” CMU Bond Beam (5th Bond Beam)
Roderick F
04/25/2024
8
Balfour Beatty
Concrete Sampling
3 yards of 4500 PSI concrete.
Greg Shivok
7133029880
254 Ozone Contractor 4
North Plant
254 Sump
Roderick F
04/24/2024
0400
J. Simmons Group, Inc.
Concrete Sampling
Road 4 STA 12+25-15+(Guthrie pouring)
victoria
2812212915
025 Site Civil
Site Civil
Road 4 STA 12+25-15+ (utilizing pump truck) est. 220 cu yds
Roderick F
04/24/2024
0800
Balfour Beatty
Visual Inspection - Add Notes
CMU Bond Beam
Zach R
832.975.2802
262 Ozone Generation Facility 2
North Plant
262 - Interior 8” CMU Bond Beam (4th Bond Beam)
Roderick F
04/24/2024
0900
Pepper Lawson - YP
Cathodic Protection
Cathodic weld inspection
Arron Powell
4092772988
035 Site Yard Piping
Yard Piping
C1-2AB
John Deaton
04/24/2024
1000
Pepper Lawson - YP
Cathodic Protection
10" PPW/PW
Felix Rodriguez
281.610.1033
035 Site Yard Piping
Yard Piping
Near 802
John Deaton
04/24/2024
8
Balfour Beatty
Concrete Sampling
18 Yards total of 4500 PSI concrete.
Greg Shivok
7133029880
216 Pretreatment Chemical Facility 6
North Plant
216 & 217 equipment pads and 254 Sump.
Roderick F
04/23/2024
0900
Fisk Electric
Field Density/Compaction/Subgrade
Density for Trench Base
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facillity 273
John Deaton
04/23/2024
1000
Fisk Electric
Electrical 2 - Ductbank/Exterior
Trench Base Insp.
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 273
John Deton
04/23/2024
830
McCarthy - Central
Visual Inspection - Add Notes
E&S 24hr test for Mixers
Cristina De Hoyos
9798240549
282 Filter Module 2
Central Plant
282 Deck East/West Mixer
Commissioning team
04/22/2024
0800
Fisk Electric
Electrical Equipment Torquing
Light Pole Ground Lug Torquing
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
North Plant - West Road
John Denton
Y
04/22/2024
10.00
Pepper Lawson - YP
Cathodic Protection
none
Saul Constallenus
956-375-9236
035 Site Yard Piping
Yard Piping
8 pdr 802
John Deaton
04/22/2024
11.00
Pepper Lawson - YP
Cathodic Protection
none
Arron Powell
409-277-2988
035 Site Yard Piping
Yard Piping
8 pw 216
John Deaton
Y
04/22/2024
12.00
Pepper Lawson - YP
Cathodic Protection
none
Carlos Colderon
832-573-8641
035 Site Yard Piping
Yard Piping
fire hydrants
John Deaton
04/22/2024
1300
Fisk Electric
Electrical 2 - Ductbank/Exterior
Trench Base Inspection
Scott Peterson
281-832-5329
045 Site Electrical
Site Electrical / I&C / Security
South Side of Facility 273
John Denton
Y
04/22/2024
8.00
Pepper Lawson - YP
Cathodic Protection
none
Andrew Mcwilliams
832-933-0426
035 Site Yard Piping
Yard Piping
10 pw 202
John Deaton
04/11/2024
0800
Balfour Beatty
Visual Inspection - Add Notes
BBII - On Going Work
Zach R
832.975.2802
254 Ozone Contractor 4
North Plant
254 - Epoxy Injection
Roderick F
04/10/2024
0800
Balfour Beatty
Visual Inspection - Add Notes
BBII - On Going Work
Zach R
832.975.2802
254 Ozone Contractor 4
North Plant
254 - Epoxy Injection
Roderick F